1. Why "Discovered on Delivery Day" Is the Most Expensive Problem
Machine problems can be fixed by the manufacturer. Site problems usually require modifying the building.
| Problem type | Discovered | Cost to resolve |
|---|---|---|
| Manufacturing defect | Before dispatch | Rework at factory; customer unaffected |
| Transport damage | On receipt | Insurance or replacement; days of delay |
| Site conditions do not match | Machine has arrived, mid-lift | Modify the building, modify the foundation, or return and rebuild |
The third type has a special property: the machine has already left the factory and cannot go back; the building is existing and cannot easily change. Both ends are rigid, with no room in between.
So this checklist is not for "a look before delivery" — it should be completed before the contract is signed, because some conditions, if unmet, change the selection itself (for example, tilt discharge replaced by bottom discharge).
2. The Eight Conditions
| # | Condition | Key test | Consequence if unmet |
|---|---|---|---|
| 1 | Headroom and tilt envelope | Highest point during tilting, not static height | Cannot tilt, or hits the roof structure mid-tilt |
| 2 | Doorway and route | Can the widest part pass; is the turning radius sufficient | Machine cannot enter the workshop |
| 3 | Floor loading | Dead weight + full material + dynamic factor | Cracking, settlement, loss of level |
| 4 | Lifting points | Beam available, capacity, height | Cannot unload or position |
| 5 | Power capacity | Convert kW to A, then size cable and breaker | Tripping, overheating, failure to start |
| 6 | Compressed air | Pressure and flow (not just "we have air") | Valves do not move, pressing force weak |
| 7 | Cooling water | Temperature, flow, quality, return | Cannot cool, jacket scaling |
| 8 | Drainage and ventilation | Where water goes, air changes | Standing water, vapour accumulation |
3. Condition 1: Headroom Follows the Tilt Envelope, Not the Machine Height
This is the easiest to get wrong and the hardest to remedy.
3.1 The error
For a tilting-discharge machine, static height is only its height standing still. During tilting the trough rotates about a pivot, and the point farthest from that pivot sweeps an arc — the top of that arc is the headroom actually required.
Required headroom ≈ pivot height + rotation radius R + safety margin
Where:
- Pivot height: distance from floor to the tilt axis;
- Rotation radius R: distance from pivot to the farthest corner of the trough — the diagonal extreme, not the trough height;
- Safety margin: 200–300 mm is advisable, covering lifting tolerances, floor unevenness and off-centre material.
3.2 An illustrative estimate
For a 2000 L class W-shape trough:
- trough width about 1.5 m, height about 1.2 m, axial length about 2 m class;
- pivot located low on the side, about 1.0 m above floor;
- pivot to farthest corner R ≈ 1.6–1.8 m.
Highest point during tilting:
1.0 + 1.8 + 0.25 ≈ 3.05 m
Static machine height may be only 2.2–2.5 m. That is a 0.5–0.8 m difference.
Many portal-frame buildings have their rafter soffit precisely in that band — the machine enters standing, then hits the structure while tilting.
3.3 Three remedies, in ascending cost
- Change the discharge method — tilt to bottom or screw discharge, eliminating the tilt (but this changes discharge behaviour and must be re-evaluated);
- Change the location — move to a bay with higher clearance, or raise the roof locally;
- Modify the building — most expensive, usually impractical.
Conclusion: this must be settled at selection stage, using the manufacturer's tilt-envelope drawing, not estimated from overall dimensions.
4. Condition 2: Doorway and Route
A machine is not a box; it is a box with protrusions.
Measure the widest part, not the main body:
| Check | Note |
|---|---|
| Clear width/height of doorway | Deduct frame, roller shutter box, rails |
| Narrowest point of route | Including columns, piping, cable trays |
| Turning radius | Long items need extra width at right angles |
| Floor capacity on the route | For the transport vehicle or forklift |
| Steps and ramps | Existence and gradient |
One commonly missed point: lid opening and tilting both need extra space. If the machine sits too close to a wall, the lid will not open and the trough will not tilt. Allow at least 1 m of maintenance access around the machine (more for large units).
5. Condition 3: Load for a Full Batch, Then Apply a Dynamic Factor
5.1 Three weights, not one
Foundation load = (machine dead weight + full material weight) × dynamic factor
| Item | Source | Common error |
|---|---|---|
| Machine dead weight | Manufacturer | Guessing "a few tonnes" |
| Full material weight | Effective volume × bulk density | Assuming water (1.0) |
| Dynamic factor | 1.2–1.4 (start-up, tilting, impact) | Ignored entirely |
5.2 Why "assuming water" fails
Many materials are far denser than 1:
| Material type | Bulk density order (t/m³) |
|---|---|
| Water | 1.0 |
| Calcium carbonate filled system | 1.5–2.0 |
| Metal powder, mineral filler | 2.5–4.0 |
| Silicone raw rubber | 1.0–1.2 |
A 2000 L machine charged with 1300 L:
- as water: 1.3 t;
- at 2.5 t/m³: 3.25 t.
A factor of 2.5. The floor is designed for machine plus material, so doubling the material can take total load from 10 t to over 12 t.
5.3 It is not only about collapse
Insufficient loading usually causes progressive problems, which are worse:
- Differential settlement → machine loses level → blade-to-trough clearance changes → rubbing and uneven seal wear;
- Foundation cracking → anchor bolts loosen → vibration increases → bearing life falls.
"The floor has not collapsed" does not mean "the loading is adequate".
6. Condition 4: Lifting
| Check | Requirement |
|---|---|
| Unloading position | Where the truck can stop without blocking access |
| Lifting equipment | Mobile crane capacity, working radius, boom length |
| Indoor lifting points | Overhead crane present; is the beam rated for the load |
| Lift height | Sufficient to clear the foundation |
| Ground strength | Capacity under crane outriggers (often overlooked) |
Rule of thumb: outrigger point loads often far exceed the machine weight itself. Setting outriggers over backfill or buried conduits is a common cause of accidents.
7. Condition 5: Power — kW Is Not A
This is the classic communication failure between electricians and buyers.
7.1 Convert kW to A first
Approximate rated current of a three-phase induction motor:
I ≈ P / (√3 × U × cosφ × η)
For 37 kW at 380 V, cosφ 0.85, efficiency 0.92:
I ≈ 37000 / (1.732 × 380 × 0.85 × 0.92) ≈ 72 A
37 kW corresponds to about 72 A, not 37 A.
Sizing cable on "37 kW means 37 A" halves the cross-section, resulting in heating, voltage drop and long-term insulation ageing.
7.2 Starting method matters too
| Starting method | Starting current | Suits |
|---|---|---|
| Direct-on-line | 5–7 × rated | Small motors, adequate transformer capacity |
| Star-delta | About 1/3 | Light starting load, medium to large motors |
| Soft starter | Adjustable | Smooth starting required |
| VFD | Can be limited | Speed control and limited starting current |
High-viscosity machines start under heavy load (cold, full batch), so both starting current and starting time exceed those of ordinary loads. Insufficient transformer capacity shows up as "the main breaker trips on start" or "the workshop lights flicker".
7.3 Five electrical facts to confirm
- Voltage and frequency (380 V/50 Hz and 440 V/60 Hz are not interchangeable);
- Transformer capacity and existing load;
- Incoming cable specification and run length (distance drives voltage drop);
- Whether a dedicated distribution cabinet or explosion protection is required;
- Earthing and residual-current protection arrangement.
Wrong voltage or frequency is the number-one delivery problem — the machine cannot be used on arrival and needs a transformer or new motor. Confirming at contract stage costs nothing; confirming after arrival costs a great deal.
8. Conditions 6–8: The Three That "Having One" Does Not Satisfy
8.1 Compressed air: pressure and flow together
| Parameter | Why |
|---|---|
| Pressure | Minimum for pneumatic valves, pressing, cylinders |
| Flow | Instantaneous consumption when several cylinders move together |
| Dew point | Moisture causes corrosion and winter freezing |
| Pipe bore | Too small means pressure arrives but flow does not |
"We have a compressor" is not "we have enough air". One small compressor serving several machines can show 0.7 MPa on the gauge and drop to 0.4 the moment a valve actuates.
8.2 Cooling water: four parameters
| Parameter | Effect |
|---|---|
| Inlet temperature | Sets the ceiling on cooling capability |
| Flow | Sets heat removal |
| Quality (hardness, chloride) | Scaling, corrosion |
| Return arrangement | Open/closed, return tank |
Jacket cooling is limited first by inlet temperature — with 30 °C water, holding product at 25 °C is impossible.
8.3 Drainage and ventilation
- Drainage: cleaning water, cooling overflow and condensate all need a destination. Uncontrolled floor discharge causes standing water, slips and soaked foundations.
- Ventilation: vapour, dust and heat accumulation. In hazardous areas, ventilation also affects whether the area classification can be reduced.
9. Pre-Delivery Checklist (Printable)
[SPACE]
[ ] Tilt envelope top ≤ rafter soffit − 250 mm
[ ] Doorway clear width/height ≥ widest part + 100 mm
[ ] Narrowest route point ≥ widest part + turning allowance
[ ] Maintenance access around machine ≥ 1 m
[ ] Lid opening space clear (not against a wall)
[FOUNDATION]
[ ] Floor loading ≥ (dead weight + full material) × 1.3
[ ] Foundation built to manufacturer's drawing and cured
[ ] Anchor bolt positions/sizes match the drawing
[ ] Floor levelness within specification
[ ] Drainage trench/floor drain does not conflict
[LIFTING]
[ ] Unloading position available and not blocking access
[ ] Crane capacity/working radius adequate
[ ] Indoor lifting point or overhead crane rated for load
[ ] Ground capacity under outriggers adequate
[UTILITIES]
[ ] Voltage ___V / frequency ___Hz / phases ___
[ ] Transformer capacity and existing load adequate
[ ] Incoming cable size and length meet voltage-drop limits
[ ] Compressed air: ___MPa / ___Nm³/min / dew point ___
[ ] Cooling water: inlet ___°C / flow ___m³/h / quality ___
[ ] Thermal oil (if used): heater capacity, oil grade, piping
[ ] Earthing and RCD in place
[DOCUMENTS]
[ ] Manufacturer supplied: foundation drawing, tilt envelope,
electrical drawing, utility requirement sheet
[ ] Site checked item by item against the above and signed
10. FAQ
Q1: The building is already up and headroom is short — what now?
Change the discharge method first (tilt to bottom or screw), then change location. Raising the roof locally is costly but feasible; structural demolition is rarely worthwhile. This is a selection-stage problem, not an installation-stage one.
Q2: Can steel plate make up for insufficient floor loading?
Plate spreads load; it does not increase bearing capacity. The correct fix is a larger foundation footprint (pad or raft) or ground improvement. Plate is an emergency measure, not a solution.
Q3: Can we take delivery and fix things during installation?
Not advisable. Changes after positioning are the most expensive, and site modifications easily damage already-verified precision (level, clearance, sealing).
Q4: If voltage/frequency is wrong, can a VFD fix it?
Partly — a VFD can change output frequency, but motor insulation and speed characteristics must be rechecked, and a 60 Hz motor run at 50 Hz delivers less power. This is not solved by adding a box; it must be calculated from the nameplate.
Q5: Who confirms these conditions?
The manufacturer supplies requirements (foundation drawing, envelope drawing, utility sheet); the customer confirms the site. Both parties sign, so responsibility is clear. Verbal-only communication produces conflicting accounts when something goes wrong.
Q6: Is this necessary for small machines?
Lab and pilot units (tens of litres) usually just need a level floor, with no foundation or lifting plan. But power, ventilation and drainage still need confirming, especially with vacuum and heating.